PROJECT DETAILS
- Project Name Speedplan Changehouse
- Client Sishen Iron Ore
- Location Postmasburg
- Year Built 2017
Project Information
Speedspace was recently awarded a contract from Sishen Iron Ore to construct a 1000 man change house at their Kolomela mine in Postmasburg. Due to limited space the Speedplan modular solution was proposed as this custom build prefabricated building is supplied and delivered containerised to site and to suit the customers’ requirements. Assembly of the 560sqm change house commenced on 1 Feb 2017 and should be completed by the end of March 2017. Despite the inclement weather the project is on time and within budget. We will ensure progress pictures are uploaded to keep track of our team on site.